Installation reports in an app: record the work while your teams are still on site
A worked installation report shows how multiple teams connect quantities, changes and photos, giving the office clear answers before invoicing.
When two installation teams return from the same customer, preparing the invoice should not start with a round of memory checks. One team reports six completed workstations, the other four and an obstruction. Without clear references, the office cannot tell whether ten or twelve positions were installed, what remains outstanding or which photographs show which room. Uncertainty created on site becomes additional office work later.
An installation report in an app should make the work actually performed understandable while everyone is still at the location. For a business with several teams, the useful connection is between scope, place and outstanding work. Recording that connection gives the office a sound working basis and the next team a clear starting point. It prepares the commercial decision without making that decision automatically.
webRichtung Onsite describes reports based on organisation templates, photographs in reports, PDF generation and digital signatures on the device. The Onsite module page explains these functions. The entirely hypothetical example below turns them into a report for installing office desks. Its suggested contents are a working template for your business, rather than a claim about standard fields already supplied by the software.
Turn the agreed scope into unambiguous positions
Start the report with the specific order reference and the description of work applicable to this visit. A general customer address is insufficient when several orders are running at one site. Likewise, “office installation” is unclear if some furniture should only be delivered while other pieces should be assembled. The reader needs to understand what work was actually planned for today.
Example order M318 covers twelve desks for installation: six in room A and six in room B. We identify their locations as A1 to A6 and B1 to B6. These names come from our fictional work plan. They allow teams, customer and office to refer to the same positions. Whether your business uses plan references, room names or existing item identifiers depends on the actual order.
The report records which version of the work plan was agreed for the visit. A later customer idea should not silently overwrite that starting scope. If a desk is to move elsewhere, the record helps distinguish a correction to the description from an additional service requiring a decision. This establishes clarity before someone spends time or materials on an unresolved change to the job.
With several teams, responsibility for each part of the documentation matters too. Team A covers positions in the first room; team B covers the second. A designated person brings the results together for the order. This is an organisational recommendation and does not assume automatic consolidation in the app. What matters is that each position appears exactly once in the final completed quantity.
Explore Onsite and prepare an installation report for your teams
Describe completed work, changes and remaining scope separately
A quantity becomes useful only when its condition is clear. “Twelve desks” could mean delivered items, planned work or completed installation. Use explicit descriptions such as planned, installed and not yet installed. This distinction matters when one person confirms delivery and another team later carries out assembly. Material arriving at the site does not automatically represent installation work already performed for the customer.
In the example, all twelve desks are present at the site. Ten have been installed and work on two has not started. Stored objects occupy the intended spaces B5 and B6 at the time of the visit, preventing the agreed placement there. That observed situation belongs in the report. A broad statement blaming the customer would assert more than the observation alone establishes.
Describe the deviation so that the next responsible person can act: identify the position, what prevents completion and what needs clarification. “Remainder later” answers none of those questions. For B5 and B6, coordination must establish with the customer when the spaces will be clear and arrange a further installation appointment. A date becomes an agreed date in the report only after it has actually been confirmed.
Give additional requests the same precision. Record what was requested and the decision status; do not present requested work as ordered or completed. The office can then assess the actual scope without reading an incidental note as a promise. The team documents the situation and follows the business’s agreed route for deciding changes. The report should make that decision easier to take and trace.
Worked report: twelve planned, ten installed, two outstanding
The fictional report starts: “Order M318, installation of twelve desks, rooms A and B, visit on 7 September 2026. Basis: the position plan agreed for this visit, covering A1 to A6 and B1 to B6.” This establishes purpose and scope. The business adds the actual contact and team details from its order; the example does not invent personal information for these entries.
Team A’s work is described as follows: “Six desks installed at A1 to A6 and recorded as complete after the business’s prescribed work check. No installation position remains open in room A.” This sentence describes the example outcome, not a technical assembly procedure. The specialist business determines the checks required for actual furniture using the real products and relevant working instructions.
Team B records: “Four desks installed at B1 to B4 and recorded as complete after the prescribed work check. B5 and B6 not started. Stored objects occupied the intended spaces during the visit. The two uninstalled units are along the right-hand wall beside the entrance to room B.” The real report must identify that location precisely so the returning team does not have to search for the remaining items.
The consolidated result reads: “Twelve positions planned; six installed in room A and four in room B, making ten in total. Two positions remain open: B5 and B6. Twelve minus ten equals two; the identified open positions match the quantity difference.” This small reconciliation prevents a heading showing the order quantity from accidentally becoming evidence of complete installation. The reader can follow it without supplying another assumption.
Time quantities also remain clearly labelled. Suppose team A has two people working three hours each, while team B has two people working two hours each. That gives six plus four, or ten person-hours. The sum of the two teams’ visit durations is five hours. Those five hours are neither ten person-hours nor necessarily the elapsed duration of the whole job, because the teams may work in parallel. Breaks and travel are excluded from this example.
The closing note says: “The ten installed and two outstanding positions were discussed with the intended customer contact. Coordination will clarify availability of the spaces B5 and B6 and a further appointment. No additional work or follow-up date was promised today.” The record of today’s visit is now complete, while remaining installation stays expressly open. The ten person-hours do not themselves establish an invoice amount.
Choose photo points another person can identify
The first photo point in the sample is room A with positions A1 to A6 after installation. Its description names order M318, the room, positions and condition. If all six places cannot usefully be seen in one image, the team adds suitable views. The written quantity still needs to be understandable; a confusing wide-angle image should not replace a clear account of what was installed.
The second photo point shows completed positions B1 to B4. The description distinguishes them from the open positions in the same room. The third documents the occupied installation spaces B5 and B6 at the time of the visit. Its purpose is to explain the specific obstruction. Uninvolved people, readable customer documents and unrelated background material do not help with that purpose and are unnecessary for this record.
These three photo points are documentation tasks, not a fixed maximum of three image files. A detail and an overview may explain one point together. Conversely, several similar pictures do not automatically provide evidence of additional installed units. With multiple teams this distinction matters: the same position photographed from two angles must not appear to be two separate completed installations in the overall report.
According to the module description, Onsite supports taking or uploading photographs in a report. Check the connection between each image and its description in the generated PDF. The next reader should recognise the subject without calling back. If references work differently in the form and the PDF, adjust the presentation using the actual output before making it your standard across all teams.
Close the report with the customer against the actual status
Allow time at the end of the visit to review the report together. In this example, the installer can say: “The six agreed positions in room A are finished, as are four in room B. We could not start B5 and B6 today. Those two positions remain open for further coordination.” This is more informative than asking generally whether everything looks fine to the customer.
Review the locations and remaining scope together while an uncertainty can still be checked directly on site. The customer may use a different room name or point out a mistake in the position plan. Any correction must reach the report. Signing an ambiguous quantity does not make the description clearer. First align the contents and references, then obtain the appropriate confirmation of that content.
Digital signatures on the device are among Onsite’s described functions. Show the customer the version and explain what they are confirming. In the example, ten completed positions and two outstanding positions remain visible. The technical availability of a signature does not establish the legal effect of a particular statement here. The business uses the wording appropriate to its actual order and situation.
If the intended contact is unavailable or a question remains, document that actual status and agree the next steps internally. An outstanding confirmation is not replaced by assumed agreement. Equally, an additional customer request should not disappear between the conversation and the PDF. The report makes both the achieved working state and the decisions still required understandable to everyone who takes the job forward.
Prevent specific questions before invoice preparation
The office receives a concrete answer to the common question: “Why were twelve ordered but only ten completed?” Positions B5 and B6 and the observed reason appear in the same document as the installed quantities. The responsible colleague can now check the order conditions and determine the next action. They do not have to begin another round of interviews with both installation teams to find the basic facts.
Keep three quantities distinct: twelve units present, ten units installed and the work that is actually billable under the agreement. The third does not follow from the report alone. For example, the office checks the actual order to determine whether partial invoicing is provided for. The documentation supplies facts for that decision without inventing a commercial rule or silently changing the customer’s agreed payment arrangements.
For time-related questions, the ten traceable person-hours help. They explain the recorded labour input, while the separate team durations can prevent a multiplication error. A general note saying “five hours installation” would be ambiguous here. Whether time matters to the invoice at all depends on the agreed pricing model. The report should therefore not quietly turn a quantity-based service into hourly billing just because time was recorded.
Onsite describes generating a PDF from the report. Provide the reviewed output through your existing working route and check that invoice preparation can find the correct version. This does not promise automatic quantity transfer into arbitrary invoicing systems. The person carrying out the next step needs the full status, including outstanding work and confirmation actually received, rather than an isolated photograph of one completed area.
Run a complete handover trial with two teams
Try the template on a manageable order where two teams work in different areas. Beforehand, check position names, required time quantities and photo references. After the visit, a colleague in the office reads only the completed report. They should be able to explain the total quantity, outstanding positions, observed reason and next responsible person. This tests whether the handover is usable, beyond whether the app can be filled in.
In the sample, “twelve complete” would be the wrong answer even if every input field had content. “Two missing” is also insufficient because the units are already on site and simply have not been installed. These distinctions show where the heading, quantity term or image description needs improvement. The trial produces a focused template correction, not an asserted savings percentage or a guaranteed reduction in administration.
Also check practical operation on the actual device and under conditions at the location. Do not rely on unconfirmed properties such as offline operation or automatic conflict resolution during simultaneous editing. Establish the available workflow and responsibility for consolidating results. A well-written template becomes useful in everyday work when the teams can reliably bring it into the intended process with the equipment and access they actually have.
Start with a recurring installation case
Begin with a common order type and improve the template using real follow-up questions. If the office repeatedly asks about locations, references need attention. If delivered and completed quantities are confused, the quantity wording needs clarification. Add fields only when they help someone make a specific decision. A long report with an unclear remainder would not represent a useful improvement to this handover.
On the Onsite page you can explore reports, organisation templates, photographs, PDF output and digital signatures, then create an account through the existing start route. Bring a typical installation order involving two teams and a common deviation as your starting point. The first benefit is concrete: record what was actually installed while on site, then let the office use that basis for the next step.
Discover Onsite and start with a clear installation report for your business
Frequently asked questions
How should two teams document the same order?
Use the same order reference and unambiguous areas or position numbers. Consolidate their results without counting any position worked on together twice.
Is a photograph enough to establish the installed quantity?
A photograph supports the written quantity and location. Without a clear reference, it may simply show the same area from another angle.
What happens to positions that have not been installed?
State their identifiers, the actual reason and the next clarification step. Unfinished work stays visible even when the report for today’s visit is complete.
Does Onsite automatically turn the installation report into an invoice?
This article covers reports with photographs, PDF output and digital signatures. Your existing invoicing process checks the documented work against the order and agreement.